Enbridge Inc.
Spacer
Spacer Shipper

2009 Refiner and Customer Update

Maps

Tolls and Tariffs

Presentations

password protected

Mainline System

The Enbridge mainline system continues to go through significant change as mainline expansions are completed. Mainline capacity out of Western Canada will change from 2.12 million barrels per day (bpd) at the end of 2008 to 2.61 million bpd by mid-2010.

Annual Capacity (000’ bpd)

YearQuarterAnnual Capacity
2005Q11.80 million bpd
2006Q11.93 million bpd
2007Q11.99 million bpd
2008Q12.12 million bpd
2009Q12.34 million bpd
2010Q22.61 million bpd

Note: Operating Capacities are 5 % higher

In today’s marketplace, supply projections are being revised downward and thus our activities are focused on optimizing the use of tankage facilities and pipelines. In addition, discussions are taking place with our customers on new tolling models which reflect the current business environment. The Canadian Incentive Tolling Agreement expires at the end of 2009 and is currently being re-negotiated.

Map

The following summarizes the various initiatives and their progress:

Southern Access Expansion

This Edmonton to Griffith multiphase expansion program will complete into Flanagan at the end of Q1 2009 increasing the capacity out of Superior by 400,000 bpd initially and ultimately by 1,200,000 bpd. The program includes:

4.0 million barrels of linefill will be required to complete the program in 2009.

More information about Southern Access Expansion

Alberta Clipper

This Edmonton to Superior expansion program complements the Southern Access expansion. Construction activities in 2008 and 2009 will culminate in a mid-2010 completion adding 450,000 bpd of capacity out of Western Canada. This program includes 1600 km (990 miles) of 36-inch diameter pipe.

6.3 million barrels of linefill will be required upon its completion.

More information about Alberta Clipper

Line 2 Expansion

A 500 km (313 mile) pipeline between Cromer and Clearbrook (Light Sour Line) along with mainline pump stations was completed at the end of 2008. The project increased Line 2 capacity to more than replace Line 13 capacity which will be put into Southern Lights service. The cost for this expansion is borne by the Southern Lights project.

Line 13 will be turned over to Southern Lights by July 1, 2010 or when Alberta Clipper goes into service, whichever is earlier.

Line 4 Extension

This expansion project adds an additional pipeline between Edmonton and Hardisty enabling the movement of new synthetics and heavy crudes from new oil sands projects that ship to Edmonton. The project includes 135 km (85 miles) of 36-inch diameter pipe, terminal connections at Edmonton and three pump stations. It will match the Line 4 capacity of 880,000 bpd. It will complete at the end of Q1 2009 and require 819,000 barrels of linefill.

Line 3 Conversion

As light supply builds it is expected that Line 3 will be converted to light service. The Edmonton to Hardisty section will be operational March 31, 2009. Timing and scope of the Hardisty to Superior section is currently being evaluated.

Tankage & Terminaling

New oil sands projects with new and expanded feeder systems into Edmonton require new connections at Edmonton. The requirement for these facilities and associated tankage is being evaluated with our customers. An initiative to evaluate commingling of crudes to minimize the addition of new facilities is underway and should be completed by the end of the 2009.

Pipeline Expansions

With less aggressive supply forecasts the need for incremental pipeline facilities is diminished. The pipelines that are expected to operate close to capacity in 2009 and 2010 include Line 5 (Superior to Sarnia), Line 6b (Griffith to Sarnia) and the pipelines feeding and exiting Griffith. The potential reversal of Line 9 continues to be evaluated and depends on firming up of supply and market requirements.

System Optimization

Enbridge is reviewing various approaches to maximize value to its customers. These approaches include system optimization to reduce capital and operating costs and responsive tolling models to reflect the current business environment. Discussions are expected to continue with customers through 2009 to identify and develop appropriate solutions.