Ingleside Phase 7 Tank Expansion Project

The Ingleside Phase 7 Tank Expansion Project expands the crude oil storage capacity at Enbridge Ingleside Energy Center (EIEC).

The project includes the construction of five additional 495,000 bbl tanks and related equipment at EIEC that will connect to existing facility infrastructure.

Construction is scheduled to start in September 2024 and is estimated to take 18 to 24 months to complete.

The tanks will be phased into service as they are constructed. The first tank is anticipated to be placed in service in late 2025.

All tanks have been permitted and we will coordinate with local agencies for local building permits.

If you have questions about the project, you can reach us at 361-461-0995 or EIECCommHotline@enbridge.com

Project Overview

  • Type: Crude oil tanks
  • In-service target date: Late 2025, phased into service as constructed
  • Ownership: Enbridge (100%)
Infographic with aerial view of tank farmClick above image to enlarge.


Project Information:

Project map

Infographic with aerial view of tank farm
Click image to enlarge.