Aspen Point Program

Return to project

Pipeline Segments

A total of approximately 18 kilometres (km) of new pipeline segments will be installed, which would include:

  • approximately 9 km of new 24-inch-diameter pipeline looping of the existing Aitken Creek pipeline.
  • approximately 8 km of new 36-inch-diameter pipeline looping of the existing Fort St. John Mainline.
  • approximately 1 km of new 30-inch-diameter pipeline which will connect the Wǫchiigii Compressor Station (CS-1B) into the existing Alberta Mainline.