Aspen Point Program
Return to projectPipeline Segments
A total of approximately 18 kilometres (km) of new pipeline segments is currently anticipated, which would include:
- approximately 8.9 km of new 24-inch-diameter pipeline looping of the existing Aitken Creek pipeline.
- approximately 7.7 km of new 36-inch-diameter pipeline looping of the existing Fort St. John Mainline.
- approximately 1.4 km of new 30-inch-diameter pipeline which will connect Compressor Station (CS-1B) into the existing Alberta Mainline.