East Tennessee Natural Gas System Alignment Program
Return to projectThe ETNG SA Program is in the early phases of development. Our focus is to engage local stakeholders to discuss the details of the proposed program, and work with landowners and the public to identify the best routes and compressor station locations. There will be many chances for public review and input during the multi-year regulatory review processes.
ETNG will obtain all required regulatory approvals from the Federal Energy Regulatory Commission (FERC) and other federal, state and local agencies.
Pending the approval and receipt of all necessary permits, construction would begin in 2025 with a target date to be fully in service in the fall of 2027.
Estimated Project Timeline
- Q1 2022: Program announcement
- Q2 2022: FERC pre-file
- Q3 2022: Open houses
- Q2 2023: FERC filing
- Q2 2025: Start of construction
- Q2 2026 to Q4 2027: In service