Project permit applications: U.S. Army Corps of Engineers
In response to the request from the Bad River Band of the Lake Superior Tribe of Chippewa Indians to remove Line 5 from its Reservation and subsequent lawsuit, Enbridge has submitted formal applications to relocate a 12-mile segment of Line 5, replacing it with approximately 41 miles of pipe outside the Reservation.
The proposed route was selected to avoid sensitive areas like Copper Falls State Park. Enbridge has come to agreement with landowners for critical land rights needed for the relocation of Line 5 in northern Wisconsin.
Enbridge has submitted formal applications to relocate a 12-mile segment of Line 5, replacing it with approximately 41 miles of pipe outside the Reservation. Several permitting agencies review the project. Construction will not begin until permits are received.
U.S. Army Corps of Engineers
The Corps regulates placement of fill material in wetlands and other waters, as well as work and structures in navigable waters. The Corps does not regulate the overall construction or operation of pipelines, nor does it regulate the siting of any type of pipeline or any substance being transported within a pipeline. The Corps is one of several permitting agencies to review the project.
USACE December 2022 Data Request Responses
- Cover letter: IR responses
- Data request responses
- Attachment 2A1: White River IR Mitigation and Contingency Plan
- Attachment 2A2: Deer Creek IR Mitigation and Contingency Plan
- Attachment 2A3: Marengo River IR Mitigation and Contingency Plan
- Attachment 2A4: Brunsweiler River IR Mitigation and Contingency Plan
- Attachment 2A5: Highway 13 IR Mitigation and Contingency Plan
- Attachment 2A6: Trout Brook IR Mitigation and Contingency Plan
- Attachment 2A7: Billy Creek IR Mitigation and Contingency Plan
- Attachment 2A8: Silver Creek IR Mitigation and Contingency Plan
- Attachment 2A9: Krause Creek IR Mitigation and Contingency Plan
- Attachment 2A10: Bad River IR Mitigation and Contingency Plan
- Attachment 2A11: Tyler Forks IR Mitigation and Contingency Plan
- Attachment 2A12: Potato River IR Mitigation and Contingency Plan
- Attachment 2A13: Vaughn Creek IR Mitigation and Contingency Plan
- Attachment 8A
- Attachment 8B
- Attachment 8C
- Attachment 9A
- Attachment 11A
- Attachment 12A
- Attachment 12B
The complete project application can be found on the USACE website.