Line 21 (Norman Wells Pipeline)

Return to project

Schedule/Timeline

  • Q4 2023: Notification of intent to renew land use permit
  • Q1 2024: In-person engagement with stakeholders
  • Q2 2024: Community meetings/information sessions in the Sahtu and Dehcho Regions
  • Q4 2024: In-person engagement with stakeholders
  • Q1 2025: Submit record of engagements and documents to stakeholder groups for review and input
  • Q1 2025: Notification of intent to submit application to the Mackenzie Valley Land and Water Board
  • Q2 2025: Submit application to Mackenzie Valley Land and Water Board