Woodfibre LNG
Return to projectProject Timeline
2014-2016—Community consultation
2020-2021—Receives provincial, federal and Indigenous (Squamish Nation) environmental assessment approvals
April 2022—Issues notice to proceed to prime contractor
2023-2027—Project construction
2027—Anticipated in service