Sequoia Solar Project

Return to project

Project Calendar

Enbridge is currently constructing the first phase of the Sequoia Solar Project which is planned to be completed in Q3 2025. Commissioning and energization activities will happen in Q4 2025, with the commercial operation date expected to be in early 2026.

For Phase 2, tree clearing and site preparation will begin in Q1 2025, with commercial operation planned for Q4 2026.

Enbridge will provide updated information as it becomes available; please check back for future updates.